Water System Update March 10

Work Continues on our water system as we near the half-way point. The contractor will complete work on Madrone early next week then start on the south end of Spruce. Hilltop will become the center of activities on or about … Continue reading

Posted in General Interest, PCM | Tagged | Comments Off on Water System Update March 10

Water Leaks Cost Us All Money

Gene Fisher and the PCM committee have created a document for the purpose of helping all of us fight above-ground leaks on our lots.  This helpful 4 page document goes over the main causes of leaks caused by ageing hoses, … Continue reading

Posted in General Interest, PCM | 1 Comment

Water System is Now Under Our Control

News from Gene Fisher…. Hello All, I am pleased to declare that the water system is now under our control! We can now separate the Park into thirteen water control zones that can be controlled separately from the others. We … Continue reading

Posted in General Interest, News, PCM | 6 Comments

Water System Work Resumes Next Monday… Feb 18

from Gene Fisher… Work to replace our water services will begin again on Monday, Feb 18. Monday and Tuesday the contractor will finish work on west Hilltop. On Tuesday or Wednesday they will begin on Dogwood. Madrone and Spruce will … Continue reading

Posted in General Interest, News, PCM | Comments Off on Water System Work Resumes Next Monday… Feb 18

Water System Update Feb 4

from Gene Fisher… Water System Project Outlook Work this week will continue on western Hilltop. The contractor who is doing the work had a vacation schedule for the following week and so the replacement of services will pause for a … Continue reading

Posted in General Interest, News, PCM | 1 Comment

Water Project Update – February 1

From Gene Fisher… We regret having the water turned off to the entire Park. We know it is inconvenient for people. We try to shut off the entire Park as infrequently a possible and for as short a period as … Continue reading

Posted in News, PCM | Tagged | Comments Off on Water Project Update – February 1

Water Service Replacement Project Update

project update from Gene Fisher… Work to replace our failing water services began on Jan 8 on Cottonwood. We chose to begin the project in the southern half of the Park because we have identified the valves control individual sections … Continue reading

Posted in General Interest, PCM | Tagged | Comments Off on Water Service Replacement Project Update