Water System Update Feb 4

from Gene Fisher…

Water System Project Outlook

Work this week will continue on western Hilltop. The contractor who is doing the work had a vacation schedule for the following week and so the replacement of services will pause for a week. In the interim, the Park manager and volunteers will construct a new service to lots 88 and 89.

Work will begin on Dogwood once Hilltop is finished. next will be Madrone followed by Spruce and the eastern part of Hilltop. Once the work on upper Hilltop is completed, the need to shut off the water to the whole Park will not be so frequent.

The Budget Committee has developed a plan for paying for the project to be considered by the Board at its February meeting.